East Japan Railway Company
March 9, 2010
On March 10, 2009, East Japan Railway Company (JR East) received an Order from the Hokuriku Regional Development Bureau of the Ministry of Land, Infrastructure, Transport and Tourism canceling our exclusive use of river water at the Shinanogawa Power Plant based on the River Law, etc., and we have since stopped water intakes for power generation.
Based on the order, we have submitted the following to the Hokuriku Regional Development Bureau of the Ministry of Land, Infrastructure, Transport and Tourism:
JR East had been preparing an application under River Law Article 23 (Permission for Exclusive Use of River Water) but it had become difficult to gain consent from concerned river users by the deadline set in the Order.
This is to report that JR East proposed to the Hokuriku Regional Development Bureau of the Ministry of Land, Infrastructure, Transport and Tourism that the application deadline based on the Order be postponed from March 9, 2010 to April 9, 2010, and we were instructed to carry out the requirements stated in the instructions.
As a company, we will continue to make every effort to gain the consent of concerned river users so that we are able to apply for water usage permission by the approved deadline.
2009.2.13 | : | Notice of administrative order from Hokuriku Regional Development Bureau of the Ministry of Land, Infrastructure, Transport and Tourism | |
2009.2.16·18 | : | Visit to concerned municipalities to deliver apologies | |
2009.3.10 | : | Order received from Hokuriku Regional Development Bureau of the Ministry of Land, Infrastructure, Transport and Tourism; water intakes stopped at Shinanogawa Power Plant | |
2009.3.11 | : | Discipline of personnel | |
2009.4.1 | : | Establishment of Shinanogawa Power Station Improvement Department | |
: | Establishment of Shinanogawa Power Station Improvement Office in Ojiya City | ||
: | Establishment of Energy Management Center | ||
2009.6.5 | : | Establishment of Shinanogawa Power Station Improvement Office, Tokamachi Office | |
2009.6.11 | : | "Report of Results of Explanation of Improper Incidents to Niigata Prefecture, Riverside Municipalities and Concerned River Users" | |
2009.6.18 | : | Letters sent to people of Tokamachi City, Ojiya City and Kawaguchi Town | |
2009.10.27 | : | "Report on Documents, etc. Relating to Structures Newly Built or Remodeled Without Permission" | |
2009.11.25·26 | : | Apologies and explanations given to people of Tokamachi City, Ojiya City and Kawaguchi Town | |
2010.2.10 | : | "Report on Measures to Prevent Recurrence of Improper Water Intakes at Shinanogawa Power Plant" | |
2010.3.9 | : | Deadline extended to apply to Hokuriku Region Planning Bureau of Ministry of Land, Infrastructure, Transport and Tourism |